FMS Winter Break Projects

Facilities management & services (FMS) Winter Break Projects

This is a preliminary announcement regarding upcoming projects that will be under construction during winter break.  Please review the following list for possible impacts to class scheduling, events, or other related issues.  Call or send e-mail replies to the appropriate FMS Project Manager listed below if you need more information.

 

Project Name:  Ayres East Pathway Improvements

Summary:   The narrow pedestrian path east of Ayres between 1st Street and the Physical Science Building will be widened and improved with new fencing and brick planters. 

Schedule:    The path will be blocked for construction beginning Dec. 22nd and will take about 6-8 weeks to finish. 

Impacts:      All pedestrian traffic will need to be detoured until the project is complete.

Project Manager:  Karen Gilmet, 530-898-3885, kgilmet@csuchico.edu

 

Project Name:  Glenn 2nd & 3rd Floor Removal of Lockers

Summary:   All lockers in the hallways will be removed and alcoves will be built similar to the first floor.  Accessible drinking fountains with bottle fillers will be installed.

Schedule:    Dec. 22nd through Jan. 14th. 

Impacts:      There will be unavoidable construction noise in both hallways.

Project Manager:  Karen Gilmet, 530-898-3885, kgilmet@csuchico.edu

 

Project Name:  Tehama 224 & 226 Refresh (Includes 224A & 228A)

Summary:   Improvements to classroom mediation technology, new ceilings and lights, minor remodeling and painting.

Schedule:    Dec. 22nd through Jan. 14th. 

Impacts:      There will be unavoidable construction noise and also minor impacts to rooms 210, 212, 228 and 230. Noise may transfer to 1st and 3rd floors.

Project Manager:  Karen Gilmet, 530-898-3885, kgilmet@csuchico.edu

 

Project Name: Kendall 103 Conference Room Mediation

Summary:   Project includes improvements to conference room technology, new lighting and finishes.

Schedule:    Dec. 22nd through Jan. 16th

Impacts:      Intermittent noise in the vicinity of the work.

Project Manager:  Stephanie Lingsch, 530-898-3889, slingsch@csuchico.edu

 

Project Name: Well Casing Replacement

Summary:   A replacement casing will be installed in the existing campus irrigation well.

Schedule:    Dec. 22nd through Jan. 19th

Impacts:      Construction fencing will be placed along the pathways adjacent to the campus well house located on the South side of Butte Hall adjacent to the Vehicle Bridge and Little Chico Creek. All pedestrian traffic will need to be rerouted until the project is complete. Noise may transfer to Butte Hall and Plumas Hall.

Project Manager:  Phil Strawn, 530-898-3882, rstrawn@csuchico.edu

 

Project Name: O’Connell Halon Panel Removal

Summary:   The Halon fire alarm panel in O’Connell 255 will be removed. The current fire alarm system for room O’Connell 255 will be replaced per code with a new system that will be tied into the existing building fire alarm system.

Schedule:    Dec. 22nd through Jan. 19th

Impacts:      There will be impacts to O’Connell 255 and 249. FMS will have to coordinate with the College of ECC Tech Shop for room use during construction. Minor construction noise may be heard at times in the hallways adjacent to O’Connell 255.

Project Manager:  Phil Strawn, 530-898-3882, rstrawn@csuchico.edu

 

Project Name: Selvester’s Fire Alarm Upgrade

Summary:   A new fire alarm system will be installed in Selvester’s Cafe

Schedule:    Dec. 22nd through Jan. 19th

Impacts:      Selvester’s will be occupied by construction crews and will be unavailable for events or daily use.

Project Manager:  Brendan Coakley, 530-898-3890, bcoakley@csuchico.edu