We have many, many projects in design and construction. Here is a current update of those projects that are larger in size. There are many smaller projects that are on the projects listing and their status can be found at: www.csuchico.edu/fms/Projects/MainProjectDatabase.pdf

CUSTODIAL SERVICES:All stripping and waxing done this summer was transitioning to the use of Green Seal floor products. Approximately 1400 gallons of the new Green Seal floor wax was applied. We did however, still need to use the traditional stripper to remove the old wax. Next summer the transition should be complete and all floor products will be Green Seal certified!

BOILER CHILLER PLANT-REPLACE CHILLER: Plans are at the Chancellor's office for review. Work is planned for this winter.

BOILER CHILLER PLANT- PLATE TO PLATE HEAT EXCHANGER: Plans are with NMR. Work is planned to be coordinated with chiller replacement and done this winter.

PAC CHILLER: Plans will begin this month, NMR to do the design. Our goal is to do this work this winter as well.

UNIVERSITY STADIUM-RESTROOMS: Funding is being finalized and project has been designed. Will need Phase I assessments for Archeological and Environmental review. The schedule is to have it open by Commencement 2008.

CAMPUSWIDE-FIRE ALARM CENTRALIZATION: Successful completion of this safety related project which upgraded equipment and allows for centralization of the alarms back to UPD and the FMS office. The final testing of the system was completed in the buildings this week. Annual and 5 year certification of all sprinklered buildings was completed.

BMU-MONITORING BASED COMMISSIONING (METERING PROJECT): A kick off meeting and information has been gathered and sent, the next phase is metering and a snapshot of operations as the baseline, so after the project a comparison can be made this is at 25% completion.

CARD ACCESS STATUS: -SHC,Ayres, Holt, Glenn and Tehama at 100% completion -Taylor using key box only since it is due to be remodeled as a Major Cap project in 2 years -Work remaining to be done in Modoc, MLIB, CCE, Colusa, Acker

REPLACE FIRE ALARM SYSTEM: This project is also at 90% completion. -

35 MAIN STREET HVAC WORK: -Project is in construction and at 40% completion. Phase I is nearing completion, then Phase II will begin.

PHYSICAL SCIENCE LAB BOILER REPAIR: -Lab boiler was rebuilt and is back into service for use.

Other Project Links



CSU, Chico | Admissions | Bookstore | Catalog | Class Schedule
Administration | Distance Programs | Library | E-mail | Help

Facilities Management & Services
California State University, Chico
940 West First Street
Chico, CA 95929-0925
530-898-6222

Webmaster
Updated 10/09/08