Science Building Update as of 11-7-2019

The project is moving along well and progressing quickly.  In the interior of the building crews are working on the mechanical, plumbing and electrical rough in, framing walls and soffits, dry walling at shafts and above ceiling locations.  On the exterior they are finishing framing and installing exterior sheathing.  The roof is substantially complete.  Windows will be installed as soon as the crews prepare the building envelope for the winter months.  The next steps on the building include ongoing work on interior MEP rough-in, interior drywall, and exterior brick and panel installation.