Human Resources Service Center

CHRS Move to Production (MTP) Preparation Activities

CHRS implementation team at Chico State

March 2025 Pay Period & Data Freeze:

  • Any March 2025 entries in Time and Labor or Absence Management will not be converted into CHRS. All entry for March should be done once we are live in CHRS.
  • No new hires March 17 - March 31; earliest start date is April 1.
  • Noon Tuesday, March 18: No future hires, job data, or personal data entry (no additions or updates).
  • March 19 – March 24: A system downtime message to be displayed.
  • March 24 GO LIVE: Portal and website updates to occur.
  • March data will be monitored by HRIS.
  • March Deadlines:
    • March 3, 5 p.m.: All transactions (except new hires) paperwork submitted to Employment or FAAF must be completed.
    • March 10, 5 p.m.: Final deadline for new hire processing.
    • March 18, 5 p.m.: Final 9.0 HR data pull and system freeze.

Access to PeopleSoft Environments:

  • March 19 @ 5:00 p.m. – March 24: Human Resources (HR) will be unavailable.
    • HRIS will notify the campus when access to the new CHRS system is available.
  • March 22 @ 12:01 a.m. - 5 p.m.: Campus Solutions (CS) will be unavailable.
  • Common Financial System (CFS) access will not be impacted.

Data Impacts:

  • March 18: Completion of Chico State HR Data Entry by the end of the day.
  • March 19: Data Warehouse will load data as usual, including CS (Student), CFS (Finance), and the final HR load from 9.0.
  • March 19, 5 p.m.: Chico State loses data access to the 9.0 instance, both application and underlying database, as the CO performs CHRS conversion activities.
  • March 20 – March 24: The data warehouse will not load data from CS, CFS, HR 9.0, or CHRS, including student, finance, and employee data. Data feeding Cognos will run on 3/19, and reports will not receive updated data until 3/24, assuming the CO provides clearance.
  • March 22, 12:01 a.m. – 5 p.m.: CS Offline.
  • March 22, 5 p.m.: Campus receives the CHRS instance, and post-conversion activities begin by the CHRS team. Full campus access to CHRS is not expected until March 23.
  • March 23: Potential Snowflake Access to CHRS data, dependent upon clearance by the CO data team.
  • March 24: Data warehouse will refresh data from CHRS (via Snowflake) and CS. Campus will be notified when available for use.
  • Insight Reports:
    • Many reports are being updated to include CHRS ID and Chico State ID.
    • March 20 – March 24: Reporting system will be available for use (no downtime), but data will be frozen.

 CHRS core team at Chico State

This schedule will be updated as new details emerge. Please direct any questions to the CHRS transition team: chrs@csuchico.edu.