LMS II Strategic Review Committee
Project Timeline
Phase I – Kick-off (Jan 28)· Orientation· Discuss Project Objective· Finalize solution criteria
Phase II – Investigation (Feb 11)· Research and document solution capabilitieso Online resourceso Vendor demonstrationso Reference siteso Surveys
Phase III – Scenario Development (Feb 25)· Analyze information and data collected· Identify and document key areas of capability or concern
Phase IV – Recommendation (Mar 18)· Scenarios to recommend to Bill P. for consideration
*Final Recommendation due by March 31, 2005